Cross-BU operational status · Real-time view

Cement — Plant Operations

82%

OEE

Obajana Plant

Kogi

18.2KMT output

RUNNING
76%

OEE

Ewekoro Plant

Ogun

14.1KMT output

RUNNING
74%

OEE

Ibese Plant

Ogun

10.5KMT output

RUNNING

Fertilizer — Delivery Status

Kaduna Plant → Distribution Network

Kaduna · 8.2KMT loaded

ONLINE

Kano Plant → Distribution Network

Kano · 4.1KMT loaded

Logistics delay

PARTIAL

KANO ROUTE — DELAYED

1,200MT NPK · 48hr delay · Heavy rains Kaduna–Kano corridor

Cross-BU Shared Logistics

Obajana (Cement)Kaduna (Fertilizer)

AVAILABLE

6 trucks · Return-trip available for NPK delivery

Ewekoro (Cement)Lagos (Distribution)

ACTIVE

12 trucks · Active delivery — cement southbound

Decision pending: Re-assign 6 available Cement trucks to Kano route for NPK delivery. See Decisions page.